Pick when you start planning and what kind of project it is. Adjust each step, and see when you could move in, what to do while you wait, and the official permit office for your area. Add the dates to your calendar in one click.
Your custom home timeline, month by month
From first meeting to move-in, with what to do while you wait.
The steps
- Find and buy a lot (if you don’t have one). Check each candidate with the lot checker and a feasibility review.
- Choose a builder. Shortlist three that work in your town and ask them all the same questions.
- Design and final price. Plans, specifications, allowances and the contract.
- Permits. For a teardown that usually means a demolition permit, a grading or site plan, and the building permit. See our knockdown rebuild permit guide.
- Demolition. Utilities disconnected, any asbestos dealt with, then the old house comes down.
- Construction. Foundation to final inspection.
- Move in. Certificate of occupancy, punch list and warranty papers.
How long construction really takes
The U.S. Census Bureau tracks how long houses take from start to finish. For contractor-built homes finished in 2025: 9% took 3 months or less, 25% took 4 to 6 months, 23% took 7 to 9 months, 17% took 10 to 12 months and 26% took 13 months or more (U.S. Census Bureau, Survey of Construction: months from start to completion, 2025). Large custom homes on tight infill lots tend to land in the longer groups, so the planner starts at 9 months and lets you change it.
The other steps start at typical planning values, not data. Replace them with your builder’s schedule as soon as you have one.
Calendar and sharing
“Add to calendar” downloads a small calendar file with a reminder at the start of each step. The page saves on your device and the link holds your plan, so you can share it. Nothing you enter is sent to us.
Frequently asked questions
How long does a knockdown rebuild take in total?
Often two years or more from first builder meeting to move-in once you add design and permits to construction. Use the planner with your own numbers.
Why do permits take so long?
A teardown usually needs several approvals in order, and each review can come back with comments. Your builder will know current times in your jurisdiction.